News
Photo report | March, 2026 | RC Simore
09.04.2026
Construction progress of the Simore club house:
– Installation and glazing of window structures on floors 2–6 are 80% complete
– Installation of stained glass structures on the 6th floor with large-format double-glazed units is 70% complete
– Freon pipelines have been installed from the roof to the apartments
– Engineering works on water supply and sewage risers for floors 1–6 are in progress
– Installation of the automatic fire alarm and notification system is underway on residential floors
– Plastering of apartment walls and partitions with ABC gypsum plaster is in progress
– Installation of the ventilated facade has begun