Construction Progress of SIMORE Residential Complex – June
– Installation of the ground-floor curtain wall structures is ongoing.
– Glazing of the curtain walls in the stairwells has commenced.
– The parking garage smoke extraction system is 80% complete.
– Ventilation works for the parking garage, gym, and children's room are 90% complete.
– Gypsum plastering works in the apartments are nearing completion.
– Floor tiling in the technical rooms and shelter is 80% complete.
– Façade insulation works are 40% complete.
– Façade cladding works are ongoing.
– Installation of underfloor heating systems in the gym and children's room has been completed.
– Installation of underfloor heating systems in the apartments is ongoing.
– Mitsubishi elevators have been delivered to the site.
– Installation of electrical systems has commenced.
– Landscaping and site improvement works in the surrounding area are ongoing.