The construction of Felicity residential complex continues at an active pace! In February, our construction teams achieved significant results, bringing future residents closer to their dream home.
🔹 Sections 1.3 and 1.4
✅ Installation of vertical monolithic structures of the 9th floor is completed.
✅ Installation of a monolithic roof slab is completed.
✅ The construction of brickwork on the 2nd-5th floors continues.
✅ Brickwork on the 6th floor has begun.
✅ Work has already begun on the arrangement of monolithic structures for access to the roof and monolithic parapets.
🔹 Sections 1.1 and 1.2
✅ Installation of vertical monolithic structures of the basement has begun.
🔹 Sections 3.1 (stylobate parking lot of the third stage)
✅ Preparatory work for the construction of the pit has been completed.
✅ Its arrangement has already begun.
🏗 We continue to work to create a comfortable and modern living space for you. Follow our updates to keep abreast of all stages of construction!