The construction of the Simore clubhouse is confidently moving forward. February was marked by active work at several key stages, and the team continues to carry out all processes according to the planned schedule.
🔹 Main achievements in February:
✅ Installation of vertical concrete structures on the 5th floor has been completed.
✅ Installation of a monolithic floor slab on the 5th floor has been completed.
✅ Vertical reinforced concrete structures of the 6th floor were erected.
✅ Formwork for the floor slab of the 6th floor is in progress.
✅ Brickwork on the walls of the 1st and 2nd floors has started.
✅ Brickwork of cell partitions in the underground parking lot is underway.
We adhere to high quality standards and continue to create a comfortable living environment for future owners. There are still many important milestones ahead, and we will keep you informed of every significant progress in the construction.