Photo report | July, 2025 | Simore RC
07.08.2025
photo report
In the heart of Lviv’s Frankivskyi district, the silhouette of the SIMORE club house has already taken shape.
Another month of progress is behind us, so we’re ready to share the construction highlights from July:
- 80% of the brick walls and partitions on the 4th and 5th floors have been completed
- External walls made of 2NF ceramic blocks are 100% complete
- Chimney brickwork on the roof has been finished
- Roofing works have started
- 50% of the roof insulation has been completed, with proper slopes for water drainage created using a cement-sand screed