News
Photo report | January, 2025 | RC Symbol
06.02.2025
photo report
The Symbol residential complex has started a new construction season with an active pace of work. In January 2025, a number of important milestones were completed, bringing us closer to the completion of the project, namely
- Installation of floor electrical cabinets completed
- Water and electricity meters have been installed
- Works on parking lot lighting have been completed
- Installation of cell doors in the 1st section and parking lot completed
- Technical doors of the parking lot are installed
- Installation of doors on the 1st floor (concierge) completed
- Work on heating the ramp to the parking lot has been completed
- Installation of paving stones and tiles in the 1st section completed
- Installation of ventilators in the apartments
- Installation of street lighting is completed.
In addition, works on landscaping of the adjacent territory and installation of tiles in the 2nd section are underway.
Our team continues to work on creating a comfortable and modern living space for future residents. Follow the updates!