The Felicity residential complex is growing steadily!
Step by step, floor by floor — it's getting closer to your dream every single day. Here's what we’ve accomplished in May:
– Brickwork on the 7th and 8th floors of sections 1.3 and 1.4 has been completed.
– Brickwork on the 5th and 9th floors of the same sections is ongoing.
– Monolithic structures for the roof access and 2nd floor parapets (sections 1.3 and 1.4) have been completed.
– Installation of Schiedel chimney systems and ventilation blocks in section 1.4 is finished; work continues in section 1.3.
– Window installation completed on the 3rd to 6th floors of section 1.4 and the 3rd to 4th floors of section 1.3.
– In section 1.2, vertical structures and the floor slab of the 1st floor have been completed.
– Vertical monolithic elements of the 1st floor have been completed in section 1.1.
– Chimney masonry on the roof of section 1.4 has begun.
– Concrete preparation for the foundation slabs of section 3.1 has been completed.