Construction progress of the Felicity Residential Complex for September:
– Completion of cement-lime plaster installation in section 1.3 is underway;
– Brick masonry works on the first floor of sections 1.3 and 1.4 continue;
– Finishing works of chimneys in sections 1.3 and 1.4 have begun;
– Installation of the wet façade system in section 1.4 has started;
– Monolithic slab of the 3rd-floor ceiling in section 1.1 has been completed;
– Monolithic slab of the 4th-floor ceiling in section 1.2 has been completed;
– Installation of monolithic vertical elements on the 4th floor of section 1.1 has started;
– Installation of monolithic vertical elements on the 5th floor of section 1.2 has started;
– Brick masonry works on the 2nd floor of sections 1.1 and 1.2 have begun;
– Installation of monolithic vertical elements of the 1st floor in section 3.1 has been completed;
– Monolithic slab of the 1st-floor ceiling in section 3.1 has been completed;
– Installation of monolithic vertical elements of the 2nd floor in section 3.1 has started.