Construction progress of the Simore Club House for September:
– Completed 50% of the masonry works for walls and partitions on the 6th floor.
– Continuing brick wall and partition installation on the 4th floor.
– Finished waterproofing of the roof with PVC membrane.
– Installed terrace rainwater drainage system.
– Completed terrace insulation with PIR thermal insulation boards.
– Performed sloping screeds on terraces of the 2nd–5th floors.
– Started preparation for installation of aluminum Reynaers window structures.
– Conducting preparatory works for cement-lime plaster application.
– Laying external water supply and gas engineering networks.